1. The construction of Billy's Greenwood Residency is speedily in progress specially Cottages
& Duplexes.
2. The project consists on the following Building Categories: |
| |
(i) Condominium: |
2 floor parking + 14 storeyed residential – FOUR Towers |
| |
(ii) Cottages: |
14 Buildings Consistency G + 3 + Pent Houses. |
| |
(iii) Duplexes: |
7 Buildings Consistency G + 1 / II + III + Pent Houses. |
| |
(iv) Shopping Complex
(v) Building for High School
(vi) Masjid
(vii) Swimming pools and Gymnasium
(viii) Indoor Games
(ix) Club House & huge playing area for children specially
|
- Constructions of the Project started w.e.f July 2007 i.e. After obtaining approval of
revised Design Drawings due to Earth Quake dt: 8-10-05.
- Till today about 60% works have been completed and construction work is in progress detailed as below: -
CONDOMINIUMS:
TOWER - I:
Structure work at level + 125 going on i.e. at 10 th floors.
Block Masonry work completed up to +85 levels.
Electric conduct pipes already placed.
TOWER - II:
Foundation started.
TOWER - III:
Structure Work at +45 levels going on.
Block Masonry work completed up to +35 levels completed.
TOWER - IV:
Raft & Columns up to + 5 levels completed.
COTTAGES:
BLOCK 01:
All structure work completed.
Internal plaster completed.
External plaster completed.
Bathrooms & Kitchen tiles work completed.
All flooring work completed.
Plumbing work completed.
Electrical work completed.
Marbles steps stairs completed.
Internal paint work completed (Final coat Balance)
External paint work completed (Final coat Balance)
Doors frames work completed.
BLOCK 02:
All structure work completed.
Internal plaster completed.
External plaster completed.
Bathrooms & Kitchen tiles work completed.
Flooring work in progress.
Plumbing work completed.
Electrical work in progress.
Internal paint work completed (Final coat Balance)
External paint work completed (Final coat Balance)
Doors frames work completed.
BLOCK 03:
All structure work completed.
Internal plaster completed.
External plaster completed.
Bathrooms & Kitchen tiles work completed.
Flooring work in progress.
Plumbing work completed.
Electrical work in progress.
Internal paint work completed (Final coat Balance)
External paint work completed (Final coat Balance)
Doors frames work completed.
BLOCK 04:
All structure work completed.
Internal plaster completed.
External plaster completed.
Bathrooms & Kitchen tiles work completed.
Flooring work in progress.
Plumbing work completed.
Electrical work in progress.
Internal paint work completed (Final coat Balance)
External paint work completed (Final coat Balance)
Doors frames work completed
BLOCK 05:
All structure work completed.
Internal plaster completed.
External plaster completed.
Plumbing work in progress.
Electrical work in progress.
Internal paint work completed (Final coat Balance)
External paint work completed (Final coat Balance)
Doors frames work completed.
BLOCK 06:
All structure work completed.
Internal plaster completed.
External plaster in progress.
Plumbing work in progress.
Electrical work in progress.
Doors frames work completed.
BLOCK 07:
All structure work completed.
Plumbing work in progress.
Electrical work in progress.
BLOCK 08:
All structure work completed.
Shuttering fixing on pent house, slab work in progress.
Electrical work in progress.
BLOCK 09:
3 rd floor slab is ready for poring.
Electrical work in progress.
BLOCK 10:
Structure work completed till 3 rd floor columns.
Electrical work in progress.
BLOCK 11:
Columns fixing work on 3 rd floor work in progress.
Electrical work in progress.
BLOCK 12:
Structure work up to 2 nd floor columns completed.
Electrical work in progress.
BLOCK 13:
Shuttering work in progress on 2 nd floor slab.
Electrical work in progress.
BLOCK 14:
Shuttering work in progress on 3 rd floor.
Electrical work in progress.
DUPLEXES:
BLOCK 01:
All structure work completed.
Internal plaster completed.
External plaster completed.
Plumbing work completed.
Electrical work in progress.
BLOCK 02:
All structure work completed.
Internal plaster completed.
External plaster completed.
Electrical work in progress.
BLOCK 03:
All structure work completed.
Plaster work in progress.
Electrical work in progress.
BLOCK 04:
All structure work completed.
Pent house slab work in progress.
Electrical work in progress.
BLOCK 05:
All structure work completed.
Pent house slab work in progress.
Electrical work in progress.
BLOCK 06:
All structure work completed.
Pent house slab work in progress.
Electrical work in progress.
BLOCK 07:
All structure work completed.
Pent house slab work in progress.
Electrical work in progress.
CLUB HOUSE:
Ground Floor slab shuttering work in progress.
SCHOOL:
Foundation work in progress.
MOSQUE:
1 st & 2 nd floor completed.
Graphics & Glass work in progress.
Minars work in progress.
MARKET:
Ground floor work completed.
1 st floor work in progress.
SWIMMING POOL:
Completed & ready for use.
WATER LAKE:
Completed to be enjoyed.
WATER FALS:
All four water falls are completed
TENNIS COURT & BASKET BALL COURT:
Completed & ready for use.
BIRDS CAGES:
Completed & different kinds of birds are in cages.
PLAYING AREA:
All playing area for children's is completed including skating Floor.
QUALITY CONTROL:
1. The works under progress are being carried out under highly Experienced and Qualified
team of supervision staff. Specifications are also being strictly followed. The quality of material is also being cheeked before its use.
2. Practice of preparation of cubes at site from randomly selected batched of concrete for
laborty testing 7 days/ 28 days is being followed. The cubes are being tested from
reputed laboratories as well as from the N.E.D. University of Engineering and
Technology. Karachi.
3. The Sample of construction Material like, Steel, Cement, Aggregate are also being got
tested from the renowned laboratories.